61 MW Kinangop Wind Park

A safety relocation plan and wayleave programme for a 61 MW wind project, delivered with a focus on fair compensation and transparent community engagement.

Project overview

Amanda Engineering supported the 61 MW Kinangop Wind Park with the development and management of its Safety Relocation Plan and with wayleave activities along a 12 km 132kV transmission line.

The assignment required close coordination with landowners, local administration and the project company. Our team managed community engagement, valuation reviews, offer letters, phased payments and completion documentation.

Client
Kinangop Wind Park / Iberdrola
Location
Nyandarua County, Kenya
Period
2014–2015
Scope
61 MW wind park / 12 km 132kV wayleave
Amanda role
Safety relocation planning, wayleave activities and community engagement
Status
Completed
Sector
Wind / Social performance
Scope of services

What we delivered.

The assignment was delivered by Amanda Engineering and its associates, with the client and project partners.

  • Development and management of the Safety Relocation Plan (SRP).
  • A nine-person relocation team working across three field teams.
  • Engagement with 38 landowners and administration of 38 barazas.
  • Valuation review, offer letters and management of signing.
  • Phased payments for resettled households and submission to the SRP financial manager.
  • Surveying, development planning of services and management of the completion audit.
  • 12 km 132kV transmission line wayleave activities.
Project notes

Relocation planning for a 61 MW wind project

The engineering and delivery context behind the assignment.

The Kinangop wind project required a safety relocation plan that could be implemented fairly and documented to the satisfaction of the project company and its financiers.

The scope included development and management of the SRP, a nine-person relocation team, engagement with 38 landowners, 38 barazas, valuation review, offer letters, phased payments, surveying, service planning and a completion audit.

The work also covered a 12 km 132kV wayleave, including presentation of offer letters, valuation of affected structures and compilation of the study report.

The assignment supported compliance with Kenyan law and the spirit of IFC Performance Standard 5, with consistent and equitable compensation for affected parties.

Relocation planningThe SRP set out the process, responsibilities and timetable.
Landowner engagementMeetings and barazas provided a clear communication channel.
Compensation deliveryValuation, offers and phased payments were managed and recorded.
Completion auditThe process was documented and reviewed at close-out.
Key challenges

What made the assignment demanding.

Safety relocations and wayleaves had to be agreed without holding up the wind park construction programme.

  • Planning safety relocations close to turbine locations and access roads.
  • Securing wayleave arrangements across 12 km of private and community land.
  • Reconciling compensation entitlements with the construction schedule.
Outcome

Project result.

The assignment supported compliance with Kenyan law and the spirit of IFC Performance Standard 5, with consistent, equitable and fair compensation for affected parties.