Key takeaways
  • Resettlement planning must begin before the route is fixed.
  • The cut-off date and entitlement matrix must be clear and consistent.
  • A completion audit is part of accountability, not an optional extra.

Resettlement is one of the most visible tests of a transmission project's social licence. A line can be engineered to specification and still fail if the people affected by it do not understand the process, do not trust the valuation or do not receive what they were promised.

High-voltage transmission line in Kenya
428 kmTransmission corridor

Why resettlement planning must start early

Transmission corridors cross farms, settlements, grazing land and businesses. The route may be selected for engineering reasons, but its social consequences are determined by land tenure, livelihoods and the way the project engages with affected people. If these issues are left until construction, the project can face delays, disputes and reputational damage that are difficult to reverse.

Early resettlement planning gives the project time to survey, consult, value, disclose and adjust. It also allows the engineering team to consider route options and tower positions that reduce impacts before the design is frozen.

The legal and policy framework

A resettlement action plan must satisfy national law and the requirements of the financiers. In Kenya, that includes the Constitution, land law, the Land Act, applicable county processes and the project's own commitments. International standards may include the IFC Performance Standards, particularly Performance Standard 5 on land acquisition and involuntary resettlement, and African Development Bank requirements.

The framework should be explained in plain language. Affected people need to know their rights, the cut-off date, the eligibility criteria, the valuation method, the compensation options and the grievance process.

Baseline, census and cut-off date

A credible RAP starts with a census and socio-economic baseline. The team records affected households, land parcels, structures, crops, businesses and community assets. It identifies vulnerable groups, including women-headed households, the elderly, people with disabilities and households with insecure tenure.

The cut-off date must be established and communicated. It prevents new claims from being created after the survey and gives the project a clear basis for eligibility. The data should be collected with a consistent method and checked before valuation begins.

Valuation and entitlement matrix

Valuation is not only a technical exercise. It must be consistent, transparent and defensible. The RAP should describe the valuation methodology, the type and nature of compensation, the preferred method of valuation and the reasons for choosing it. It should also set out the legal and regulatory framework for compensation.

The entitlement matrix translates the policy into specific categories. It shows what a household or business is entitled to for land, structures, crops, loss of livelihood, relocation and transitional support. The matrix should be clear enough to be applied consistently across the corridor.

Field team carrying out socio-economic surveys
Field evidenceThe baseline is the foundation.

Census and socio-economic data determine who is eligible, what they are entitled to and how success will be measured. Weak baseline data undermines every later stage of the RAP.

Engagement, disclosure and grievances

Engagement should begin before decisions are final. Meetings, barazas, focus group discussions and individual consultations provide different levels of detail and different opportunities for questions. The project should disclose the draft plan, the valuation process and the payment arrangements in a way that affected people can understand.

A grievance mechanism must be accessible, recorded and answered. It should not be treated as a complaints desk at the end of the process. Grievances often reveal problems in the survey, valuation or communication that need to be fixed before implementation.

Implementation and livelihood restoration

Compensation is only one part of resettlement. The plan should address relocation, land access, service connections, business disruption and livelihood restoration. Payments need to be traceable, and the project should monitor whether households have actually restored their living standards.

Implementation requires coordination between the project company, valuers, surveyors, community liaison teams, local administration and the affected people. Records should be kept for every offer, payment and agreement.

Monitoring and completion audit

Monitoring tracks progress against the plan. A completion audit tests whether the commitments were met and whether the objectives were achieved. It should be independent enough to be credible and detailed enough to show what was done, what remains outstanding and what corrective action is needed.

Resettlement is not a one-off payment. It is a process that must remain accountable from the first survey to the completion audit.

Experience on Kenyan corridors

Amanda Engineering has worked on the Loiyangalani-Suswa 400kV transmission line, including RAP preparation and addendum reporting for a 428 km corridor, and on the Kinangop wind park, where we supported a safety relocation plan and 12 km 132kV wayleave activities. Those assignments reinforced a simple lesson: early, documented and transparent engagement is cheaper than late dispute resolution.

What a resettlement plan should contain

The exact structure depends on the project and the financier, but a credible RAP normally contains the following components.

ComponentPurposeOutput
Project descriptionExplain the line, route, works and land requirementsMaps, alignment, tower positions, construction methodology
Legal frameworkShow how national law and international standards applyLegal review and entitlement principles
Census and baselineIdentify affected people and assetsHousehold data, asset inventory, socio-economic profile
ValuationSet a consistent method for compensationValuation methodology, rates, review process
Entitlement matrixTranslate policy into specific entitlementsCategories for land, structures, crops, livelihoods and vulnerability
Livelihood restorationAddress the longer-term impact on incomesProgrammes, responsibilities, budget and indicators
Grievance mechanismProvide a route for concerns and disputesProcedures, records, response times and escalation
Monitoring and auditShow whether commitments were metIndicators, reporting schedule and completion audit

Roles and responsibilities

Resettlement works when responsibilities are clear. The project company owns the commitments. The RAP team provides the method, data and implementation support. Valuers, surveyors, community liaison staff and local administration each have a defined role. The grievance team must be independent enough to be trusted.

Good practice also separates the people who assess eligibility from the people who authorise payments. That reduces the risk of inconsistent decisions and makes the process easier to audit.

Indicators to track

  • Households surveyed and validated against the cut-off date.
  • Assets valued and offers issued.
  • Payments made and acknowledged.
  • Households relocated and services connected.
  • Grievances received and closed within the agreed time.
  • Livelihood restoration participation and outcomes.
Next insight

What a solar feasibility study should answer

Need support on a project like this?

Our team can help with feasibility, design, procurement, construction supervision and project management. Tell us about the site, scope and stage of your project.

Discuss a project